DETAIL PROGRESS KNMP

100
Lokasi Progress Bergerak
41.55%
Progress Nasional
0.37%
Rata-rata per Site
0
Site Selesai 100%
TREND PROGRESS NASIONAL
TOP KENAIKAN PROGRESS
Mattiro Bombang SULAWESI SELATAN
+79%
Lero Pinrang SULAWESI SELATAN
+75%
Limbua SULAWESI BARAT
+70%
Tadang Palie SULAWESI SELATAN
+69%
Punagaya SULAWESI SELATAN
+69%
Terapung SULAWESI TENGGARA
+68%
Tamarupa SULAWESI SELATAN
+67%
Lumpue SULAWESI SELATAN
+66%
Bontorannu SULAWESI SELATAN
+65%
Data SULAWESI SELATAN
+70%
Arungkeke Pallantikang SULAWESI SELATAN
+64%
Watolo SULAWESI TENGGARA
+65%
Takkalasi SULAWESI SELATAN
+65%
Bungeng SULAWESI SELATAN
+63%
Lasama SULAWESI TENGGARA
+63%
RANKING PROVINSI
Provinsi Total Site Avg Completion Hub Penyangga
SULAWESI TENGGARA 15 52.33% 4 11
SULAWESI SELATAN 50 50.54% 7 43
SULAWESI BARAT 6 45.33% 0 6
SULAWESI TENGAH 14 44.50% 2 12
GORONTALO 11 36.09% 1 10
SULAWESI UTARA 15 0.53% 3 12
TOP 10 PROVINSI
ProvinsiAvg Completion
SULAWESI TENGGARA 52.33%
SULAWESI SELATAN 50.54%
SULAWESI BARAT 45.33%
SULAWESI TENGAH 44.50%
GORONTALO 36.09%
SULAWESI UTARA 0.53%
DISTRIBUSI PROGRESS NASIONAL
0%
11
1-25%
12
26-50%
42
51-75%
45
76-99%
1
100%
0
PROGRESS TERBARU
Lero Pinrang
SULAWESI SELATAN

46% Pekerjaan Tambatan Perahu, Docking Kapal, Kantor Pengelola dan Kios Perbekalan
* Pek. Tambatan Perahu * Pek. Pembesian besi kolom pemasangan bekisting dan pengecoran kolom precast pada tambatan perahu * Pek. Bangunan docking kapal * Pek. Bangunan kantor pengelola lanjutan plesteran * Pek. Saluran drainase pemasangan batu bela dan plesteran * Pek. Saluran pembuangan air hujan pada bangunan kios perbekalan * Pek. Lanjutan Pasangan bata merah pada bangunan rumah genset * Pek. Pemasangan bekisting dan pengecoran kolom pada bangunan shelter pendaratan ikan * Fabrikasi pembesian
2026-10-14 20:13:00
Sumpang Binangae
SULAWESI SELATAN

5% Pekerjaan Pembesian
Fabrikasi Pembesian
2026-10-14 19:38:00
Siddo
SULAWESI SELATAN

10% Pekerjaan Pembesian
Fabrikasi Pembesian
2026-10-14 19:36:00
Songka
SULAWESI SELATAN

24% Pekerjaan DPT
pasangan batu dinding penahan tanah.
2026-10-14 19:29:00
Belopa
SULAWESI SELATAN

33% Pekerjaan Gudang Beku, Shelter Pendaratan Ikan, Saluran dan Kantor Pengelola
Pekerjaan Gudang Beku Pekerjaan Atap Shelter Pekerjaan Saluran Pekerjaan Atap Kantor Pengelola
2026-10-14 18:47:00
Lakawali Pantai
SULAWESI SELATAN

47% Pekerjaan Dinding Penahan Tanah
Pengecoran tapak DPT
2026-10-14 18:20:00
Tasiwalie
SULAWESI SELATAN

23% Pekerjaan Revetment, Pekerjaan DPT dan Pabrik Es
* Pek. Tangga revetment * Pek. Pemasangan bekisting dinding penahan tanah * Pek. Pengecoran sloof bangunan pabrik es portable
2026-10-14 16:10:00
Benteng
SULAWESI SELATAN

30% Pek. Kios Perbekalan dan Shelter

2026-10-14 10:52:00
Darubiah
SULAWESI SELATAN

20% Pek DPT

2026-10-14 10:47:00
Letta
SULAWESI SELATAN

35% Pek. DPT

2026-10-14 10:46:00
DETAIL SITE
Site Provinsi Status Completion Updated
SITE00085
Moilong
SULAWESI TENGAH PENYANGGA 24% 2026-11-04 11:08:40 Lihat Site
SITE00127
Huwongo
GORONTALO PENYANGGA 23% 2026-11-09 14:43:59 Lihat Site
SITE00106
Muara Bone
GORONTALO PENYANGGA 18% 2026-11-12 10:39:31 Lihat Site
SITE00111
Olimoo'O
GORONTALO PENYANGGA 17% 2026-11-09 14:42:16 Lihat Site
SITE00145
Lero Donggala
SULAWESI TENGAH PENYANGGA 17% 2026-11-25 09:56:03 Lihat Site
SITE00114
Biluhu Tengah
GORONTALO PENYANGGA 15% 2026-10-20 11:59:38 Lihat Site
SITE00180
Naha 1
SULAWESI UTARA PENYANGGA 3% 2026-11-12 11:13:45 Lihat Site
SITE00181
Gangga 2
SULAWESI UTARA PENYANGGA 2% 2026-10-30 13:11:17 Lihat Site
SITE00179
Kahuhu
SULAWESI UTARA PENYANGGA 2% 2026-11-12 11:18:13 Lihat Site
SITE00182
Lamanggo
SULAWESI UTARA HUB 1% 2026-10-29 13:21:33 Lihat Site