DETAIL PROGRESS KNMP

100
Lokasi Progress Bergerak
41.55%
Progress Nasional
0.37%
Rata-rata per Site
0
Site Selesai 100%
TREND PROGRESS NASIONAL
TOP KENAIKAN PROGRESS
Mattiro Bombang SULAWESI SELATAN
+79%
Lero Pinrang SULAWESI SELATAN
+75%
Limbua SULAWESI BARAT
+70%
Punagaya SULAWESI SELATAN
+69%
Tadang Palie SULAWESI SELATAN
+69%
Tamarupa SULAWESI SELATAN
+67%
Terapung SULAWESI TENGGARA
+68%
Lumpue SULAWESI SELATAN
+66%
Bontorannu SULAWESI SELATAN
+65%
Watolo SULAWESI TENGGARA
+65%
Takkalasi SULAWESI SELATAN
+65%
Data SULAWESI SELATAN
+70%
Arungkeke Pallantikang SULAWESI SELATAN
+64%
Bungeng SULAWESI SELATAN
+63%
Lasama SULAWESI TENGGARA
+63%
RANKING PROVINSI
Provinsi Total Site Avg Completion Hub Penyangga
SULAWESI TENGGARA 15 52.33% 4 11
SULAWESI SELATAN 50 50.54% 7 43
SULAWESI BARAT 6 45.33% 0 6
SULAWESI TENGAH 14 44.50% 2 12
GORONTALO 11 36.09% 1 10
SULAWESI UTARA 15 0.53% 3 12
TOP 10 PROVINSI
ProvinsiAvg Completion
SULAWESI TENGGARA 52.33%
SULAWESI SELATAN 50.54%
SULAWESI BARAT 45.33%
SULAWESI TENGAH 44.50%
GORONTALO 36.09%
SULAWESI UTARA 0.53%
DISTRIBUSI PROGRESS NASIONAL
0%
11
1-25%
12
26-50%
42
51-75%
45
76-99%
1
100%
0
PROGRESS TERBARU
Tada
SULAWESI TENGAH

51% Pek. Tambatan perahu

2026-11-11 09:49:00
Sausu Tambu
SULAWESI TENGAH

42% Pek. Tambatan perahu

2026-11-11 09:48:00
Lero Donggala
SULAWESI TENGAH

9% Lev Lahan

2026-11-11 09:48:00
Mattiro Bombang
SULAWESI SELATAN

79% Pekerjaan Tambatan Perahu dan Atap Spandek
* Pemasangan Bekisting Balok Atas Dan Balok Anak Tambatan Perahu * Pemasangan Atap Spandek Kanopi * Pembesian Plat Lantai Tambatan Perahu
2026-11-10 20:20:00
Lero Pinrang
SULAWESI SELATAN

55% Pekerjaan DPT, Tambatan Perahu, Shelter Pendaratan Ikan, Kantor Pengelola dan Bangunan Genset
* Pek. Rangka atap baja ringan dan trap entrance bangunan genset * Pek. Kanstin dan tiang lampu pju tambatan perahu * Pek.Saluran drainase pemasangan batu bela dan plesteran dinding * Pek. Bangunan kantor pengelola * Pek. Plesteran dinding Kuda" beton bangunan shelter pendaratan ikan * Pek. Trap entrance bangunan shelter pendaratan * Pek. Kuda" beton bangunan docking kapal * Pek. Jalan kawasan pemadatan timbunan makadam
2026-11-10 20:01:00
Tamarupa
SULAWESI SELATAN

52% Pekerjaan Revetment, DPT dan Kios Perbekalan
* Pemasangan Batu Belah Aanstamping Reventmen * Pengecoran Pondasi Penahan Tanah * Pemasangan Pintu Rolling Door Bangunan Kios Perbekalan
2026-11-10 19:58:00
Lampenai
SULAWESI SELATAN

37% Pekerjaan DPT
Pek. Pengecoran DPT
2026-11-10 19:12:00
Bawalipu
SULAWESI SELATAN

27% Pekerjaan Rangka Atap Beton dan Kios Perbekalan
* Perakitan pembesian rangka atap beton * pasangan batu merah kios perbekalan
2026-11-10 19:08:00
Balo-Balo
SULAWESI SELATAN

40% Pekerjaan Pabrik Es Portable dan Kios Perbekalan
* urugan tanah pabrik es portable * pemasangan batu merah kios perbekalan
2026-11-10 19:07:00
Lakara
SULAWESI TENGGARA

59% Pekerjaan Kios Perbekalan, Revetment, DPT dan pembesian
= pek. Pemasangan bekisting Kolom kios pengelola = pek. Pabrikasi pembesian ring balk = pek. Perapian dpt = pek. Pemasangan batu revetment
2026-11-10 19:04:00
DETAIL SITE
Site Provinsi Status Completion Updated
SITE00158
Tasiwalie
SULAWESI SELATAN PENYANGGA 38% 2026-11-25 12:01:45 Lihat Site
SITE00028
To'bia
SULAWESI SELATAN PENYANGGA 38% 2026-11-17 11:35:51 Lihat Site
SITE00064
Lampenai
SULAWESI SELATAN PENYANGGA 38% 2026-11-19 15:59:34 Lihat Site
SITE00150
Siddo
SULAWESI SELATAN PENYANGGA 37% 2026-11-19 10:00:06 Lihat Site
SITE00036
Cimpu Utara
SULAWESI SELATAN PENYANGGA 37% 2026-11-16 09:44:31 Lihat Site
SITE00011
Tubo Poang
SULAWESI BARAT PENYANGGA 35% 2026-11-24 10:44:13 Lihat Site
SITE00076
Boyantongo
SULAWESI TENGAH HUB 35% 2026-11-25 09:40:53 Lihat Site
SITE00008
Bonde Utara
SULAWESI BARAT PENYANGGA 34% 2026-11-19 09:35:50 Lihat Site
SITE00020
Songka
SULAWESI SELATAN PENYANGGA 33% 2026-11-24 09:55:51 Lihat Site
SITE00140
Tanjung Bunga
SULAWESI TENGGARA PENYANGGA 33% 2026-11-25 10:06:03 Lihat Site